The second tower at Harbour Row topped out this month, eleven weeks ahead of programme.

The final concrete pour on the east tower finished on a Saturday morning, with residents of the first tower watching from the quay.
Facade installation continues through the autumn, and the first homes in the east tower are due to complete next spring.
Most of the eleven weeks came from the core. We poured the lift and stair core in a single continuous slip, which kept the cranes free for the floor slabs, and the same crew moved straight from the west tower to the east without a break.
The public quay opens in two stages: the boardwalk this winter, and the planted terraces once the cranes come down.
Buyers in the east tower will receive their first floor visit invitations in January. Each visit takes about an hour, with the site manager for that floor, and you can bring anyone you like.